Works included:

  • Demolition works
  • New suspended ceilings throughout
  • Creation of sleep rooms with sound rating and observation rooms with 1 way glass
  • Low level partitions capped with timber tops for separation of areas
  • New Forbo vinyl flooring to corridors and Burmatex carpets to office areas
  • Decoration of all areas including feature walls
  • New double door sets with glazed side panels
  • Installation of air conditioning units
  • New Kitchen area
  • New mechanical and electrical installation
  • New roller blinds

The works were carried out over the summer shutdown and works are now complete ready for staff to return in September.